2500 W. Carver Street - Duplex

Blue Chariot Rehab to Rental #14 – 2500 W. Carver Street – Duplex (Unit B / Upper), Durham – North Carolina

Blue Chariot has finally completed our longest running rehab to rental project at: 2500 W. Carver Street – Duplex (Unit B / Upper), Durham, NC 27705 – which is located off Guest Road. This unfinished Duplex was purchased in mid-August of 2017, and was just finished in July 2018. It took almost a full year to complete this project due to many unforeseen occurrences (detailed below); and it having been our first attempt at rehabbing an occupied property (the Lower Level) – something we’ll NEVER do again…

 

BEFORE: BathroomBEFORE: Dining RoomThe Upper Level (B Unit) of this Duplex was unfinished, but had a layout / space and ceiling height to create a nice 2 Bedroom / 1 Bathroom Unit (6 Rooms) of approximately 1,023 SqFt. See the separate post on the Lower Level (A Unit) of this Duplex. It appears the prior owner had attempted to complete the Upper Level, by adding some Kitchen Cabinets, a Toilet, Tub, and a mix of Vinyl and Hardwood Flooring; however, it was never completed – and was not arranged for the best use of available space. Therefore, we gutted the entire area and started over with a clean slate.

 

BEFORE: Entry Stairs & Deck

BEFORE: Entry Stairs & Deck

DURING: Deck Replacement

DURING: Deck Replacement

The project began on the outside with things like a new roof and sealing the many cracks in the exterior walls. It was first thought the cracks were due to a serious foundation issue, but upon pre-purchase examination by a Structural Engineer, these were found to be due to the lack of gutters.

After demo of the Upper Level, the next task was to replace the original entry stairs and deck, which were not in a safe condition – and required new concrete footers and base pad. With the stairs and deck replaced, we next started the plumbing and electrical rough-in, having removed all prior plumbing and electrical throughout the Upper Level.

 

BEFORE: Door to Nowhere

BEFORE: Door to Nowhere

BEFORE: Bedroom #2 - Door

BEFORE: Bedroom #2 – Door

We then proceeded to add sound damping insulation between the floor joists, replace all the sub-floor, and begin the new framing – which included replacing a door with a window in the back bedroom that lead to nowhere (a straight drop down). We had considering creating a second deck here; however, as the project went forward, we started to exceed our planned budget (see “Problems” section below) and had to cut costs – so there was no room in the budget for this add-on of a second deck.

 

DURING: Foam Insulation

DURING: Foam Insulation

DURING: Framing

DURING: Framing

With all plumbing, electrical and framing work done, we sprayed foam insulation throughout, installed the new HVAC, Water-Heater, etc…  We wanted to keep the brick vent stack from the old Lower Level furnace, so we did some masonry work and incorporated the brick into the framing as an accent element, that turned out pretty cool…

 

AFTER: Trim, Floor & Brick

AFTER: Trim, Floor & Brick

AFTER: Tile Shower

AFTER: Tile Shower

Doors, drywall, and trim went up, then the ceiling and trim were painted white, while the walls received our normal color of “Pumpkin Seed”. We went with different flooring than usual (just to try something different) – which was an alternate style of Vinyl Plank throughout the entire unit (no carpet). And in the bathroom, we did tile.

 

Water-heater Utility Access

Water-heater Utility Access

The HVAC and Water-Heater are both hidden within utility access areas having angled doors. The W-H sits off the Dining Room behind the Kitchen Sink and Dishwasher. The HVAC system is behind the 2nd Bedroom Closet.

AFTER: Kitchen

AFTER: Kitchen

We finished things out with Stainless Steel Appliances, Granite Counters and Subway Tile Backsplash in the Kitchen, including a Drop-in Stove and Island Range Vent Hood – with Bar Seating in the Living-Room.

Although the flooring is not our favorite, the end result of this project is a great 2BR / 1BA space of over 1,000 SqFt; which sits atop another great 4BR / 1BA space of nearly 1,800 SqFt. Both units are rented to members of the same family, who were already present in the Lower Level when we purchased the property. But working above and occasionally in an occupied home made things more difficult… For example, on a few occasions during demo and sub-floor work, holes were inadvertently created in the Lower Level ceiling. We had to be very careful to make sure things did not fall through on persons below. We also had to limit work hours on many occasions; and the family had to be relocated to a hotel for a week on 3 or 4 occasions during the project.


The Problems…

Our certificate of occupancy was delayed on a few occasions, causing the project to linger for an extra month. In one case it was because the spray foam insulation was applied to the utility access area containing the HVAC system (it was not supposed to be), which creates a potential ventilation issue. Additional venting had to be added. Additional venting was also needed for the W/D utility closet, because the confined space needed more ventilation to pass inspection. In another case, a problem occurred in getting the island range vent hood installed so that electrical inspection could pass.

But the biggest problem was plumbing… We ended up replacing most of the plumbing in both levels of the property (with the exception of one short section) – including replacing the entire sewer line out to the street. And this process involved multiple attempts to snake the line, including at one point having it scoped with a camera.


Take a look (below) at some BEFORE and AFTER pictures…

AFTER: Entrance

AFTER: Entrance

BEFORE: Entrance

BEFORE: Entrance

AFTER: Kitchen to Living Room

AFTER: Kitchen to Living Room

BEFORE: Kitchen to Living Room

BEFORE: Kitchen to Living Room

AFTER: Kitchen to Living Room

AFTER: Kitchen to Living Room

BEFORE: Kitchen to Living Room

BEFORE: Kitchen to Living Room

AFTER: Living Room

AFTER: Living Room

BEFORE: Living Room

BEFORE: Living Room

AFTER: Kitchen & Hall

AFTER: Kitchen & Hall

BEFORE: Kitchen & Hall

BEFORE: Kitchen & Hall

AFTER: Dining Room

AFTER: Dining Room

BEFORE: Dining Room

BEFORE: Dining Room

AFTER: Fireplace Bricks

AFTER: Fireplace Bricks

BEFORE: Fireplace Bricks

BEFORE: Fireplace Bricks

AFTER: Bedroom #1 - New Window

AFTER: Bedroom #1 – New Window

BEFORE: Bedroom #1 - Window

BEFORE: Bedroom #1 – Window

AFTER: Bathroom

AFTER: Bathroom

BEFORE: Bathroom

BEFORE: Bathroom

AFTER: Bedroom #2 - Door Became a Window

AFTER: Bedroom #2 – Door Became a Window

BEFORE: Bedroom #2 - Door

BEFORE: Bedroom #2 – Door

AFTER: Bedroom #2 - Closet

AFTER: Bedroom #2 – Closet

BEFORE: Bedroom #2

BEFORE: Bedroom #2

AFTER: Bedroom #2 - Looking Out

AFTER: Bedroom #2 – Looking Out

BEFORE: Bedroom #2 - Looking Out

BEFORE: Bedroom #2 – Looking Out

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply